IEPC Conduct energy audit shall look into the heat balances and mass balances of the unit including coal, oil, water, chemicals and auxiliary power consumptions, visit site assess the present status and the availability of instrumentation and to prepare for the energy audit, and to conduct energy audit, understanding the assignment and reviewing Indian legal requirements for performing energy audits. Provide an overview of the methodology for performing audits and establishing baselines including performance test with specific standards and codes: e.g. ASME code or any practical standard methods to be able to analyze the causes and identify the rehabilitation options. Prepare and submit an inception report.
Prepare for the energy audit identifying a list of equipment/ Instrumentation required for audit. Conduct detail audit of all the following systems and auxiliaries;

Coal handling Plant.
Estimate the average capacity utilization of the coal handling plant
Measure the consumption of Motors, (current, power factor)
Coal measuring system and quality check

Ash handling system and ESP.
Evaluate the electricity consumption of ESP in comparison with the design
Study the collection efficiency, coal quality, ash property and conditioning including ammonium injection)
Study the ash utilization and disposal methods including consumption of water for ash disposal in wet disposal system
Power consumption and pump performance of ash handling system

Cooling water system.
Assessment of cooling tower capacity and efficiency
Evaluate circulating water pump performance and power consumption
Water circulation, condenser efficiency, and turbine heat rate
Assessment of Vacuum system.

Boiler and Turbine and their Auxiliary
Boiler combustion efficiency (unburnt carbon in ash)
Boiler outlet temperature, and excess air level
Performance evaluation and Power consumption of ID fan. FD fan, PA fan, Coal mills,
Air-preheater efficiency and leakage, flue gas temperature
Boiler Feed Pump (power consumption and performance evaluation)
Turbine cylinder efficiency and cycle efficiency.
Condenser performance and evaluation.
Condensate pumps power consumption and performance evaluation.
LP and HP heaters performance evaluation.
Raw water system and waste water treatment system.
Capacity utilization and power consumption

Instrumentation and control
Evaluate the instrumentation available in the plant
Measuring instrumentation at coal handling plant, ash handling system,, Raw water and waste water system

Compressed Air System.

Insulation of Boiler, Air and flue gas path and Steam piping.

Calculate the Boiler Efficiency , Turbine Heat Rate (efficiency) and Heat rate of the plant at 100%, 75%, 50% load
with coal-fired (and oil-fired) .
Estimate the average capacity utilization of the coal handling plant
Measure the consumption of Motors, (current, power factor)
Coal measuring system and quality check

Fuel (coal & oil) consumption, water consumption and auxiliary consumption.

Total Electrical system Audit including Lighting
Transformer Load Management
Power Factor management
Distribution losses
Harmonic analysis.

Any other test other than those specified above on the system other than the specified as above is required to establish the baseline performance of the unit prior to carrying out Energy Efficient R&M and LE Works of the Unit, it shall be carried out.

To prepare and submit a comprehensive Energy Audit Report based on the results of the performance test and energy audit, and identify causes of efficiency, availability and power output decrease.

Objective

To determine Auxiliary Power Consumption of the station.
To evaluate the auxiliary power consumption of each Unit.
To evaluate the station auxiliary power consumption for common auxiliaries
To measure power consumption for the motors > 100 KW and determine percentage motor loading.
To determine the distribution of power consumption among major drives and systemsfor each unit.

ACTIVITY II: Field Data collection

Record Energy meters readings for Gross generation, Export/Import, UATs and STson 24 hours basis for the duration of audit.
Record process parameters for all identified drives for each Unit at 5-10 minutes time interval (Total 03 nos readings) and record power consumption during this test. For drives not having on line EM, power consumption to be taken by portable power analyzer.
Record process parameters and power consumption for identified common auxiliaries.
Record total power consumption for Coal handling plant, Ash water system, Compressed air system, Air conditioning system and lighting system and power consumption for individual drives having power consumption of more than 100 KW.
Record all the HT transformer load.
Check CVT wiring of gross and export energy meters and record its size.

ACTIVITY III: APC evaluation & Data analysis:

Calculate station auxiliary power consumption through measured power at Unit auxiliary transformer and station transformer.
Calculate APC through energy balance method using below given formula Auxiliary Power Consumption =Total Gross energy – (Total export Energy – Total import Energy) - All Transformer losses
All transformer losses include the losses in all the generator transformers, all UATs and STs if any. These losses are to be calculated based upon the design specifications/Test Certificate.
Calculate Energy Un balance at Switchyard using below given formula & comment for the unbalance and suggest for the remedial measure. Energy Unbalance at Switchyard =Total Net generated energy – (Total export Energy – Total import Energy)
APC from these two methods and comment for the deviations if any and suggest for the remedial measures.
Calculate annual power consumption for Coal handling plant, Ash handling system, Compressed air system, Air conditioning system and lighting system based upon annual running hours.
Record Energy meters readings for Gross generation, Export/Import, UATs and STson 24 hours basis for the duration of audit..
Record process parameters for all identified drives for each Unit at 5-10 minutes time interval (Total 03 nos readings) and record power consumption during this test. For drives not having on line EM, power consumption to be taken by portable power analyzer.
Record process parameters and power consumption for identified common auxiliaries.
Record total power consumption for Coal handling plant, Ash water system, Compressed air system, Air conditioning system and lighting system and power consumption for individual drives having power consumption of more than 100 KW.
Record all the HT transformer load.
Check CVT wiring of gross and export energy meters and record its size.
Record Energy meters readings for Gross generation, Export/Import, UATs and STson 24 hours basis for the duration of audit..
Record process parameters for all identified drives for each Unit at 5-10 minutes time interval (Total 03 nos readings) and record power consumption during this test. For drives not having on line EM, power consumption to be taken by portable power analyzer.
Record process parameters and power consumption for identified common auxiliaries.

Testing Equipment:

Load Analyzer
Infrared Temp meter
Lux meter.
Circular weight bulb temperature meter.

Commercial offer

To Carrey Our Study of Aux.
Power consumption of 24.2MW Power plan
Unit -One


View Complete Catalog





INDO ENGINEERING PROJECT CORPORATION

The Indo Engineering Project Corporation is a Technical Consultancy Group & E P C providers with Project Engineering and Project management services.
Power Plant: Captive Power Plant, Coal and Waste Heat, Bio-Mass, Mini/Micro Hydel, Wind Energy.
Steel Plants: Sponge Iron, Hot Rolling, Cold Rolling, Induction Furnance, Calcinations Plant
Loading Systems: Coal Washery, Coal Handling, Flood Loading, Ash Handlig and Cooling Tower.
Other: Water & Waste Treatment Plant, Fire Fighting & Protection, Control System, Automations, Chemicals & Fertilizers, Water Supply System.



View Company Profile

Other Matching Products


Merchandise Inspection

Inspection & Survey Services Quality Goods Control Services Laboratory Testing Services Engineering Control & Inspection Services ....

HCP SULZER,RND68,RND76,RND90,RND105 genuines,OEM parts

We agent and sales:H.CEGIELSKI HCP SULZER,SWEDEN SULZER,CHINA SULZER products SULZER(Genuines,OEM) Type: RD44,RD56,RD66,RD68,RD76,RD90 RND68,RND76,RND90,RND105 RLA38,RLA56,R ....

Poland HCP Sulzer,Sweden Sulzer,China Sulzer pump,diesel engine,spare parts supply

Poland HCP SULZER,Sweden SULZER,China SULZER,pump,diesel engine,spare parts supply HCP SULZER,RD44,RD56,RD66,RD68,RD76,RD90 genuines,OEM parts HCP SULZER,RND68,RND76,RND90,RND105 ....

HCP SULZER,RLA38,RLA56,RLA 66,RLA 76,RLA 90 genuines,OEM parts

Sulzer Cly head,Cyl liner,piston head,piston skirt,conn rod,valve,Authorized OEM diesel parts. Sulzer valve seat,guide pipe,piston pin,exh valve casing,exh pipe,bearing Authorized ....

Sulzer crankshaft gear,silencer,preheat unit,exh brake valve,camshaft Authorized OEM diesel parts.

SULZER(Genuines,OEM) Type: RD44,RD56,RD66,RD68,RD76,RD90 RND68,RND76,RND90,RND105 RLA38,RLA56,RLA 66,RLA 76,RLA 90 RLB38,RLB56,RLB 66,RLB 76,RLB 90 RTA38,RTA48,RTA52,RTA58,RT ....

Operations & Maintenance

We are specialist service providers for power plant maintenance services, thermal plant maintenance, operation, preventive & break down maintenance, corrective maintenance, erectio ....

Project Management Consultancy Services

Project Management - Site Management - Project Planning & Scheduling Computerized Network Monitoring Project Evaluation and Progress Reporting Project Managem ....

Engineering Erection & Commissioning

Our Business Caters to engineering solution and Manpower services to: Engineering experts for POWER PLANT Indo engineering Projects Corporation Called (IEPC) the leading Design ....

Inspection

ACTIVITIES: Inspection & Survey Services Quality Goods Control Services Laboratory Testing Services Engineering Control & Ins ....

RLA Services

IEPC Conduct energy audit shall look into the heat balances and mass balances of the unit including coal, oil, water, chemicals and auxiliary power consumptions, visit site assess ....